The main electrical control centre has been installed at the site in the last quarter. Installation of all the electrical and instruments which are wired into the facility are now being constructed.
The gas engine and alternator to the power supply, manufacture in the United States and wired in Italy, is on route. Backup power installation from Western Australian’s Western Power Grid is also nearly complete.
The EP 389 joint venture (JV) is developing the Red Gully gas and condensate processing facility from the two discovery wells, Gingin West-1 and Red Gully-1, pursuant to the pipeline licence within the EP 389 permit.