Construction works on the Charlie Gas Development are progressing, although some short delays were encountered as a result of inclement weather.

The development involves the construction of 300–400 wells, a large field compression station and associated pipelines and facilities which will feed into existing gas processing and water infrastructure at Woleebee Creek.

Construction of the Charlie field compression station is underway with all major foundations expected to be complete by the end of August.

The pipelines team is advancing construction of the 34 km gas and water pipelines, with the stringing and bending of the gas pipeline complete.

The water pipeline lengths are now being delivered from Toowoomba to the easement on the pipeline route and welding of these pipe sections has commenced.

The Charlie pond and pump stations are a third of the way through completion.

The overall project is over a quarter of the way through construction.