Sudan pipeline project completed

The EPC project has been completed in 14 months by OVL, against the contractual schedule of 16 months.

The 12-in diameter pipeline system has been designed for export of 2.54 million tons/yr of MoGas (Petrol) and gasoil (Diesel), as well as other white products such as kerosene and fuel oil. It includes six pumping stations, two launcher and receiving stations, and four intermediate pigging stations.

OVL executed the EPC contract with support of ONGC’s engineering services under a technical and administrative support agreement, and worked with a consortium of Dodsal Pte Ltd, Dubai and DPL, Mumbai, as the EPC partner.