Mr Baldwin’s comments follow the release of Origin’s 2013 Annual Reserves Report and Quarterly Production Report for its exploration and production business for the period ended 30 June 2013.
During the June quarter, 93 km of gathering lines were installed, bringing the cumulative total to 161 km (equivalent to servicing 273 wells).
The APLNG transmission pipeline was 73 per cent complete at the end of June 2013, with 143 km installed – 88 km of which were installed during the June quarter. Approximately 212 km of the main pipeline has been welded.