Alltype Engineering (AE) has reached practical completion of the Waitsia Inlet Meter Station with Australian Gas Infrastructure Group (AGIG).

Located in Western Australia, the project’s scope included bulk earthworks, civil and concrete works, offsite skid fabrication and structural, mechanical, piping, electrical and instrumentation (SMPEI) assembly works (including FAT testing).

AE said the installation of the prefabricated skids onsite with corresponding SMP installation and electrical and instrumentation site construction works completed the station connection to the Dampier Bunbury Pipeline.

“The Waitsia Inlet Meter Station Project was delivered safely, on time and budget,” said AE.

Image courtesy of Alltype Engineering.

“This achievement is a credit to all the people from AE and our subcontractor partners who had been involved in the project, during a global pandemic crisis to deliver the project in an tight schedule with over 5,000 onsite man hours with zero first aid or loss time injuries.”

The company also thanked AGIG for its professionalism and cooperation throughout the project.

For more information visit the AE website.

If you have news you would like featured in The Australian Pipeliner contact Managing Editor David Convery at dconvery@gs-press.com.au

Show more

Related articles

Back to top button
Close
Close